ADU cost calculator: a budget worksheet built on your own numbers
This ADU cost calculator does not guess a price. You type in the amounts from your quotes and your city's fee schedule, and it adds them line by line, applies California's ADU fee rules to the fees, and adds the contingency you choose. The result is your budget, not ours, and every rule it applies is cited below.

Why this calculator has no default prices
Most online ADU calculators start from a dollar-per-square-foot number and multiply. That number has to come from somewhere, and it is usually a marketing figure for one product or one builder. Two backyards on the same street can differ by tens of thousands of dollars in site work alone: one has a flat, open side yard and a sewer line ten feet from the slab, the other has a slope, a tree, and a long trench to the street. A single rate hides that, so we left it out.
The one published figure we show is a reference, not an input. In its 2021 statewide survey of California ADU owners, UC Berkeley's Terner Center found a median cost of $150,000, or $250 per square foot. Use it to see whether your own total is in the same territory as what other owners reported paying, not to build your budget. Our guide to what an ADU costs explains what that survey does and does not tell you.
Your ADU budget worksheet
Your running total
- Your quoted lines
- $0
- Impact fees after the ADU rule
- $0
- Connection fees after the ADU rule
- $0
- School fees
- $0
- Contingency
- $0
- Total
- $0
- Your cost per sq ft
- enter the size
- Terner Center 2021 median
- $250 per sq ft
Fee rules appear here once you enter a fee amount.
The fee rules the worksheet applies in California
California sets limits on what a city or special district may charge an ADU, and the worksheet applies them to the full amounts you enter. The rules come from Government Code section 66311.5 (numbered 66324 before a 2025 renumbering) and Education Code section 17620, as HCD's ADU Handbook (March 2026 edition) describes them. Our page on California ADU fees goes through each one with examples.
| Fee | What the worksheet does | Rule |
|---|---|---|
| Impact fees (including park fees) | Zero at 750 sq ft or less; above that, the city's full amount times your ADU's size divided by the main home's size | Gov. Code § 66311.5(c) |
| Water and sewer connection fees | Zero for an ADU inside existing space or a JADU; otherwise in proportion to size against the main home | Gov. Code § 66311.5(b), (e) |
| School fees | Zero at 500 sq ft or less; above that, your district's rate times the ADU's size | Ed. Code § 17620 |
Two cautions. First, the law allows connection fees to be proportioned by drainage fixture units as well as by size, so your district may calculate differently; the worksheet uses size because it is the figure you will have. Second, a city may state its own threshold: San José's ADU fee page, for example, says school and parkland fees do not apply under 750 square feet. Where a city's own page is more generous than the state minimum, use the city's number.
For a lot in Texas the worksheet applies no state rule, because Texas has no statewide ADU fee law; fees there are whatever your city's schedule says. See ADU costs in Dallas–Fort Worth.
How to fill it in without fooling yourself
Get every line from a document
Each field should hold a number you can point to: a written quote, a fee schedule, an estimate from the building department. San José, for example, gives a free fee estimate when you file its Form 337. If a line is still a guess, put your guess in, but write down that it is one, and raise your contingency until it is replaced.
Watch for lines a quote leaves out
The most common gaps are the trench and sewer line from the ADU to the street connection, an electrical panel upgrade, and the final grading and drainage around the unit. A prefab quote often stops at the factory door, so delivery, crane, foundation and hookups are separate; our prefab ADU cost guide lists what to ask for in writing.
Choose a contingency on purpose
We do not suggest a percentage, because none of the sources we rely on publishes one for ADUs. A higher contingency makes sense for an older lot with unknown utilities, a slope, or a design that is not finished yet, and a lower one once every line is a signed quote.
What the worksheet leaves out
It does not estimate what the ADU will rent for, what it adds to the home's value, or what your property tax will be. Those depend on things only a lender, an appraiser or the county assessor can tell you. For the property tax side, loans and rent counted as income, see paying for an ADU. Nothing you type is sent anywhere: the worksheet runs in your browser, and it is cleared when you leave the page. If you want us to look at your lines with you, send the short form below.
Budget worksheet
Stuck on a line in your worksheet?
Call, or send the form below with the lines you are unsure of. We call or email you back to go through the budget lines; asking costs nothing.
Send us your worksheet questions
A few lines are enough: the kind of ADU you have in mind, roughly how big, and the city or ZIP. We call or email you back to go through the budget lines; sending this costs nothing.
Budget worksheet questions
Does the ADU cost calculator save or send what I type?
No. The worksheet runs in your browser and keeps nothing: there is no account, no storage and no upload, and the numbers are gone when you close the page. Only the separate request form sends anything, and only the details you choose to write in it.
Why does my total drop when I choose a conversion instead of a detached ADU?
Because California treats an ADU built inside existing space, and a junior ADU, differently for water and sewer fees: under Government Code section 66311.5(b) it is not a new residential use for connection fees or capacity charges. The worksheet sets that line to zero for those two types.
Can I use the worksheet for a lot outside California?
Yes, choose Texas: the worksheet then adds your fees exactly as you enter them, with no state rule applied. That fits any state without an ADU fee law, but check your own city's code, because a few cities have their own reductions.
Sources: California HCD, ADU Handbook, March 2026 (Gov. Code § 66311.5, Ed. Code § 17620); UC Berkeley Terner Center, statewide ADU owner survey (2021); City of San José, Fees for ADUs; Texas Legislature, SB 673 history.